Wailea Ekahi Pavilion Renovation Project - Status Archive
Updated January 15, 2020
Overview
For your convenience, this webpage contains archived information on the progress of the project with high resolution photographs.
October 2019 Update
|
The beautiful new Pavilion has taken shape. Roof installation, electrical, plumbing and mechanical rough in work,
installation of the exterior siding and trim and bathroom drywall will be performed in the next three weeks.
|
September 2019 Update
|
Progress - September 27
Our new Pavilion is taking shape! The Pavilion slab has been poured and the stairs and column pour backs are
being made. Trusses are in the process of being installed and rough carpentry and roof framing will
be ongoing for the next 2 ½ weeks.
|
August 2019 Update
|
The new Pavilion is out of the ground and taking shape! Footings are in place, major structural framework has been set,
backfilling is underway and concrete block walls are being built. Behind the scenes Crown Construction,
Michael Wright & Associates, Steve Shepherd, Erickson Structural Engineers, design engineers,
interior designer and committee members are working through the iterative process of reviewing and inspecting the
structural components and fixtures as well as finalizing interior finish details.
|
July 2019 Update
|
This month the form work for the footing was completed, the reinforcing steel was installed and inspected
and on July 26 the concrete footing was poured. The footing will cure for a minimum of seven days prior
to installation of moment frames and backfill and compaction. Design details related to the truss system
and number and placement of rooftop photovoltaic panels are being refined, as well as interior
and exterior finish selections.
|
June 2019 Update
|
Preparatory work has been completed to make way for the form work, rebar installation, inspections and the concrete
pour in the next two weeks.
Crown Construction completed the heavy demolition and removed site debris during the week of June 3 – 7. Workers began excavating and trenching for new footings.
The project continues to be on schedule.
|
May 2019 Update
|
Crown Construction has completed another week of demolition, and we anticipate one more week of heavy demolition noise.
There will still be construction noise, but not to the extent we have heard in the past few weeks.
The photos depict current site conditions as of May 30, 2019.
The Pavilion slab has been removed, footing demolition is in progress, and other masonry demolition activities occurred during the week of May 20.
Take a look at the photos below to see the progress as of May 24, 2019. You can click each image to see a full resolution version.
As of May 17, 2019, demolition of the main Pavilion structure was completed. These aerial photographs give you a bird’s eye view
of the contractor’s progress. Demolition of select areas of the slab foundation will begin May 20 and proceed for the following three weeks.
You can click each image to see a full resolution version.
|
|
|